The Brains of the Operation

The Ares I-X avionics system is known as the “brains of theoperation.” Last week the first stage avionics were installedin the third, or aft, piece of the fifth segment simulator in the VehicleAssembly Building at KSC.

Avionics controlevery active portion of the test flight, from liftoff to navigation to datacollection and parachute deployment. In addition to controlling the rocket, theavionics will be collecting, transmitting, and storing engineering data before,during, and after the flight. The information gathered by the avionics systemwill be incorporated into further computer simulations and analyses to helpNASA better understand how the Ares I crew launch vehicle will fly and interactwith its environment. 

Avionics hardwareis being installed in nearly every part of the Ares I-X flight test vehicle,from the crew module and launch abort system simulators to the aft skirt of thefirst stage.

 

You can read more about Ares I-X avionics on Wikipedia:

 

http://en.wikipedia.org/wiki/Ares_I-X

 

Ares I-X is growing smarter everyday!

Aft Skirt Hot Fire Test…Check!

Today, Ares I-X passed another significant milestone when engineers and technicians successfully completed a hot fire test of the hardware at the Aft Skirt Test Facility at Kennedy Space Center.

The hot fire test is actually a series of tests performed on the Aft Skirt –primarily the Thrust Vector Control (TVC) System. Before the test, the fuel systems are checked for leaks and filled with hydrazine (rocket fuel). The hot fire is a two-minute run of the Auxiliary Power Units (APU) using the hydrazine just as it would on launch day. The electro hydraulic servo-actuators, which control the direction the nozzle is pointing, are commanded to move to various positions to make sure they respond properly to commands. Additionally, the power units are run at 100%, 110% and 112% of capacity to assure that all redundancy modes are working properly.

When the test has been successfully completed the hydraulic systems are left as they are and the hydrazine is taken out. The system will stay in that condition until the Ares I-X vehicle is at the launch pad where the system will be refueled with hydrazine in preparation for launch.

With this milestone complete, the aft skirt will be transferred to the Rotation Processing and Surge Facility next month and attached to the aft motor segment. When attached, these two pieces of hardware make up the aft assembly and will be the first hardware to be stacked on the Mobile Launcher Platform in the Vehicle Assembly Building when that process begins in June.