NASA’s Artemis II Orion Spacecraft Prepares for Vacuum Testing

The Artemis II Orion spacecraft is pictured surrounded by the metal walls of the altitude chamber
Technicians used a 30-ton crane to lift NASA’s Orion spacecraft on Friday, June 28, 2024, from the Final Assembly and System Testing (FAST) cell to the altitude chamber inside the Neil A. Armstrong Operations and Checkout building at NASA’s Kennedy Space Center in Florida. The spacecraft, which will be used for the Artemis II mission to orbit the Moon, underwent leak checks and end-to-end performance verification of the vehicle’s subsystems.

NASA’s Orion spacecraft for the Artemis II mission was lifted out of the Final Assembly and System Testing cell on June 28 inside the Neil A. Armstrong Operations and Checkout building at NASA’s Kennedy Space Center in Florida. The integrated spacecraft has been undergoing final rounds of testing and assembly, including end-to-end performance verification of its subsystems and checking for leaks in its propulsion systems.

A 30-ton crane returned Orion into the recently renovated altitude chamber where it underwent electromagnetic testing. The spacecraft now will undergo a series of vacuum chamber qualification testing. The tests will subject the spacecraft to a near-vacuum environment by removing air, thus creating a space where the pressure is extremely low. This results in no atmosphere, similar to the one the spacecraft will experience during future lunar missions.

Testing will span approximately a week, with technicians collecting data from the spacecraft’s chamber, cabin, and the environmental control and life support system to test spacesuit functionality. The data recorded during these tests will be used to qualify the spacecraft to safely fly the Artemis II astronauts through the harsh environment of space.

NASA Kennedy Teams Test Upgraded Environmental Control System for Artemis II 

Credits: NASA

Teams with NASA’s Exploration Ground Systems (EGS) Program successfully tested the upgraded environmental control system on mobile launcher 1 while it’s at Launch Pad 39B at the agency’s Kennedy Space Center in Florida in preparation for Artemis II. This system provides air supply, thermal control, and pressurization to SLS (Space Launch System) and the Orion spacecraft during cryogenic propellant loading. 

During propellant loading, the environmental control system purges specific compartments within Orion and SLS using gaseous nitrogen to maintain the proper environmental conditions. This is critical, as the rocket and spacecraft must be in a safe and stable configuration and temperature when dealing with hazardous gasses. The severtal-week test, which started April 17, was conducted in two parts. Teams first started flowing air through the system and then followed by flowing gaseous nitrogen.   

This marks the next set of tests complete for EGS teams as part of the integrated system verification and validation testing in preparation for Artemis II, the first crewed Artemis mission that will send four astronauts around the Moon and back next year. 

The testing puts the team and ground infrastructures to work and ensures each are functioning properly and allows the team to update and refine procedures ahead of launch. Part of this series includes testing the launch pad’s environmental control system, the emergency egress system, the ignition overpressure protection and sound suppression system, among others. 

NASA’s Artemis II Orion Spacecraft Completes Electromagnetic Testing

After completing electromagnetic compatibility and interference testing, the Artemis II Orion spacecraft is returned to the FAST cell via crane inside the Neil A. Armstrong Operations and Checkout Building at NASA's Kennedy Space Center in Florida on Saturday, April 27, 2024.
After completing electromagnetic compatibility and interference testing, the Artemis II Orion spacecraft is returned to the FAST cell via crane inside the Neil A. Armstrong Operations and Checkout Building at NASA’s Kennedy Space Center in Florida on Saturday, April 27, 2024. Photo credit: Amanda Stevenson

On Friday, April 26, engineers completed a series of electromagnetic tests on the integrated Orion crew and service module for NASA’s Artemis II mission inside the Neil A. Armstrong Operations and Checkout (O&C) Building at the agency’s Kennedy Space Center in Florida. 

During testing, engineers subjected the spacecraft to electromagnetic energy using wave guides, amplifiers, and antenna horns while inside an altitude chamber.

The test helps verify that all of Orion’s electronic systems can work in sync and safeguards against potential malfunctions caused by electromagnetic disturbances in the harsh and complex environment of space. Engineers will analyze the data collected during testing to ensure all systems on Orion are not disturbed by electromagnetic energy and the spacecraft is ready to safely fly the crew around the Moon. 

The team returned the spacecraft to the Final Assembly and System Testing, or FAST cell inside the O&C building following electromagnetic testing for additional work in preparation for further performance testing inside the vacuum chamber later this summer.  

Women Launching Women: How NASA Mentors Artemis Generation

On July 16, 1969, the Apollo 11 mission lifted off on a Saturn V rocket from NASA’s Kennedy Space Center in Florida. Crowds gathered with their eyes craned toward the sky, as NASA set out to make history with their next giant leaplanding astronauts on the Moon. 

One historical member watching the launch, JoAnn Morgan, instrumentation controller for Apollo 11, and the only female in the firing room inside NASA’s Launch Control Center.

Photo show members of Kennedy Space Center team inside the Launch Control Center to watch Apollo 11 liftoff. JoAnn Morgan is seated to the left of center in third row.
Members of the Kennedy Space Center government-industry team rise from their consoles within the Launch Control Center to watch the Apollo 11 liftoff through a window. JoAnn Morgan is seated to the left of center in the third row. Photo credit: NASA

“I look at that picture of the firing room where I’m the only woman. And I hope all the pictures now that show people working on the missions to the Moon and onto Mars, in rooms like mission Control or launch Control or wherever — that there will always be several women. I hope that photos like the ones I’m in don’t exist anymore,” said Morgan. 

NASA is hard at work 55 years later returning astronauts to the Moon with the Artemis campaign which will land the first woman, first person of color, and its first international partner astronaut on the Moon – and establish the first long-term presence on the Moon. With these new missions supporting lunar exploration, Morgan’s hope for several women in the STEM field is coming true.  

Today, in that very same room where Morgan once sat as the only female engineer, dozens of women sit on console preparing to launch the mighty SLS (Space Launch System) rocket and Orion spacecraft back to the Moon for Artemis II. The room itself is not only full of a diverse group of engineers, but leading the team to liftoff is NASA’s first female Launch Director, Charlie Blackwell Thompson.

Photo shows women of Artemis launch team wearing green for
The women of Artemis launch team pose for a photo wearing green for “go” inside the Launch Control Center at NASA’s Kennedy Space Center in Florida. Photo credit: NASA/Kim Shiflett

This Women’s History Month, female leaders within the space industry met at NASA Kennedy to reflect on what mentorship means to them.  

“JoAnn, you did show us, whether you knew it at the time or not, that we belong in this room,” Blackwell-Thompson said. “Because of the work you did all those years ago, you made it possible for me.” 

The leaders meeting shared their thoughts on ways women can lead in the space industry. 

  1. Sharing is caring 
    Sharing is the basis of mentorship. Share your experiences either as a guiding tool or a lesson learned.
  2. An attitude of gratitude  
    We grow stronger when we grow together. Shine the light their way and give them a moment in the sun. A sense of gratitude and encouragement amongst others can make a huge difference in the effectiveness of the team.
  3. Stepping up to the plate  
    How can you be a person of action?  
  4. Growing pains are good  
    Just like physical growing pains, experiencing uncomfortableness in your career can be a sign of growth. Outperformance will feel uncomfortable. Trying something new will feel uncomfortable. Get comfortable being uncomfortable.
  5. Define how others view you  
    Deliver on your word. Do the right thing when nobody is looking. Be the person you would want on your team.
  6. Leadership is not defined by your title 
    Rise to the challenge within your everyday activities. Inspire those around you and offer a helping hand when it is needed. You can embody all of the characteristics of someone who leads long before you have the words manager, supervisor, or director in your official title.
  7. Identify your board of advisors  
    Just like any company trying to grow, your career deserves a board of advisors to grow. Create a space where you can talk your career navigation. Your board of advisors can change over periods of time and take shape in formal or informal relationships. 
  8. Bet on yourself 
    At every stage in your career, you hold power. Ask for a new challenge, the power to say no, and the power to ask for help.  
  9. Surround yourself with the best of the best  
    Teams can only be the best of the best when they include diverse thought. Be mindful of who you can collaborate with that will bring ideas unique from yours.  
  10. Make your mistakes matter   
    What did you learn? What can you teach others? How will this mistake lead you in the future? 

The work NASA does today, wouldn’t be possible without the mentors who have blazed the trail before. NASA Kennedy Center Director Janet Petro shares the importance of this teamwork, reminding us, “We are not doing any of this work for just ourselves, it is for the bigger goals of the agency and humanity.”  

Have a mentor you would like to thank? Send them your very own NASA thank you card: SP-2024-02-154-KSC EGS Women Launching Women Notecards_fillable.pdf 

¿Tienes un mentor al que le gustaría agradecer? Envíales tu propia tarjeta de agradecimiento de la NASA: SP-2024-03-246-KSC EGS WLW – Thank You Card Spanish Notecards_Fillable.pdf 

NASA Kennedy Teams Test High-Speed Cameras for Artemis II Mission 

Credits: NASA

Teams with NASA’s Exploration Ground Systems Program have completed the next series of integrated ground systems testing at the agency’s Kennedy Space Center in Florida. On Jan. 25, the high-speed film and high-speed digital cameras on the mobile launcher and Launch Pad 39B were successfully tested at the spaceport ahead of the Artemis II mission.  

Following Artemis I, teams updated the 68 high-speed cameras, which start during the final 12 seconds of the countdown to provide views of the rocket and surrounding ground structures during launch. The imagery also is used in detailed post-launch analysis.   

The updates on the cameras include:   

  • Software and procedures to ensure proper field of view of the rocket and spacecraft.  
  • High-speed digital camera firmware and digital recorder software to improve visual video quality.  
  • Optical control system software to ensure accurate setup. 
  • Upgraded faceplate purge hardware – a small tool near the camera lens that releases small amounts of gaseous nitrogen to remove any water that falls on the lenses.    

During a water flow test to check the sound suppression system at the pad, teams tested these cameras by setting them up in a launch countdown configuration. The test verifies the cameras’ field of view and the upgraded faceplate purge hardware all function properly. In September 2023, teams at Kennedy and at NASA’s Marshall Space Flight Center in Huntsville, Alabama also tested the cameras during a hot fire test of the upgraded solid rocket booster design for the SLS (Space Launch System) rocket for future Artemis missions.   

Personnel at Kennedy next will test the dynamic range of the cameras during a nighttime commercial rocket launch from a nearby launch site. Following each operation, teams will analyze the footage to ensure each camera performed as expected. 

Artemis II Orion Crew and Service Modules Joined Together

Mating of the crew and service modules for the Artemis II Orion spacecraft was recently completed at NASA’s Kennedy Space Center in Florida.
Intergration of the crew and service modules for the Artemis II Orion spacecraft was recently completed at NASA’s Kennedy Space Center in Florida. Photo credit: NASA

On Oct. 19, the Orion crew and service modules for the Artemis II mission were joined together inside the Neil Armstrong Operations and Checkout Building at NASA’s Kennedy Space Center in Florida.

After successfully completing hardware installations and testing over the past several months, engineers connected the two major components of Orion that will fly NASA astronauts Reid Wiseman, Victor Glover, and Christina Koch, along with CSA (Canadian Space Agency) astronaut Jeremy Hansen on a mission around the Moon and bring them home safely.

Now that the crew and service modules are integrated, the team will power up the combined crew and service module for the first time. After power on tests are complete, Orion will begin altitude chamber testing, which will put the spacecraft through conditions as close as possible to the environment it will experience in the vacuum of deep space.

All Engines Added to NASA’s Artemis II Moon Rocket Core Stage

Engineers and technicians from NASA, Aerojet Rocketdyne, and Boeing at NASA’s Michoud Assembly Facility in New Orleans have installed all four RS-25 engines to the core stage for NASA’s Space Launch System rocket that will help power the first crewed Artemis mission to the Moon. The yellow core stage is seen in a horizontal position in the final assembly area at Michoud. The engines are arranged at the bottom of the rocket stage in a square pattern, like legs on a table.
Engineers and technicians from NASA, Aerojet Rocketdyne, and Boeing at NASA’s Michoud Assembly Facility in New Orleans have installed all four RS-25 engines to the core stage for NASA’s Space Launch System rocket that will help power the first crewed Artemis mission to the Moon. The yellow core stage is seen in a horizontal position in the final assembly area at Michoud. The engines are arranged at the bottom of the rocket stage in a square pattern, like legs on a table. Photo Credit: NASA/Eric Bordelon

Teams at NASA’s Michoud Assembly Facility in New Orleans have structurally joined all four RS-25 engines onto the core stage for NASA’s Artemis II Moon rocket. The flight test is the agency’s first crewed mission under Artemis.

Technicians added the first engine to NASA’s SLS (Space Launch System) rocket core stage Sept. 11. Teams installed the second engine onto the stage Sept. 15 with the third and fourth engines Sept. 19 and Sept. 20. Technicians with NASA, Aerojet Rocketdyne, an L3Harris Technologies company and the RS-25 engines lead contractor, along with Boeing, the core stage lead contractor, now will focus efforts on the complex task of fully securing the engines to the stage and integrating the propulsion and electrical systems within the structure.

The SLS core stage, at 212 feet, is the backbone of the Moon rocket. Its two huge propellant tanks provide more than 733,000 gallons of super-chilled liquid propellant to the four RS-25 engines, while the stage’s flight computers, avionics, and electrical systems act as the “brains” of the rocket. During Artemis II, the RS-25 engines will together provide more than 2 million pounds of thrust for eight minutes of flight, helping to send the Artemis II crew beyond low-Earth orbit to venture around the Moon.

NASA is working to land the first woman and first person of color on the Moon under Artemis. SLS is part of NASA’s backbone for deep space exploration, along with Orion and the Gateway in orbit around the Moon, and commercial human landing systems. SLS is the only rocket that can send Orion, astronauts, and supplies to the Moon in a single mission.

For more on NASA SLS visit:

https://www.nasa.gov/sls

Artemis II Astronauts Successfully Conduct Launch Day Demonstration   

Artemis II astronauts, from left, NASA astronaut Victor Glover (left), CSA (Canadian Space Agency) astronaut Jeremy Hansen, NASA astronauts Christina Koch and Reid Wiseman stand on the crew access arm of the mobile launcher at Launch Pad 39B as part of an integrated ground systems test at Kennedy Space Center in Florida on Wednesday, Sept. 20. The test ensures the ground systems team is ready to support the crew timeline on launch day. Photo Credit: NASA/Frank Michaux

The Artemis II crew and teams with NASA’s Exploration Ground Systems Program successfully completed the first in a series of integrated ground system tests at the agency’s Kennedy Space Center in Florida in preparation for their mission around the Moon.  

On Wednesday, NASA astronauts Reid Wiseman, Victor Glover, and Christina Koch, along with CSA (Canadian Space Agency) astronaut Jeremy Hansen, practiced the procedures they will undergo on launch day to prepare for their ride to space. 

The crew awoke at their crew quarters inside Kennedy’s Neil Armstrong Operations and Checkouts building before putting on test versions of the Orion crew survival system spacesuits they will wear on launch day. They then departed in NASA’s new Artemis crew transportation fleet to take them to Launch Pad 39B, traversing the nine-mile journey to the pad. Wiseman and Glover headed over in the first electric vehicle as Koch and Hansen followed them in the second.  

Upon arrival at the pad, the crew headed onto the mobile launcher and proceeded up the tower to the white room inside the crew access arm. From this area, the astronauts will have access to enter and exit the Orion spacecraft – only for this test, there was no Orion or SLS (Space Launch System) rocket. 

“When we walked out that crew access arm, I just had images of all those Apollo launches and shuttle launches that I saw as a kid and it was unreal,” Glover said. “I actually had to stop and just stay in the moment to really let it all sink in.” 

Successful completion of this test ensures both the crew and the ground systems teams at Kennedy are prepared and understand the timeline of their events for launch day.  

Credits: NASA

First RS-25 Engine Installed to NASA’s Artemis II Moon Rocket

Engineers and technicians from Aerojet Rocketdyne and Boeing at NASA’s Michoud Assembly Facility in New Orleans have installed the first of four RS-25 engines to the core stage for NASA’s Space Launch System rocket that will help power the first crewed Artemis mission to the Moon. The yellow core stage is seen in a horizontal position in the final assembly area at Michoud. One RS-25 engine, engine number E2059, has been installed in the top left corner at the base of the 212-foot-tall core stage.
Engineers and technicians from Aerojet Rocketdyne and Boeing at NASA’s Michoud Assembly Facility in New Orleans have installed the first of four RS-25 engines to the core stage for NASA’s Space Launch System rocket that will help power the first crewed Artemis mission to the Moon. The yellow core stage is seen in a horizontal position in the final assembly area at Michoud. One RS-25 engine, engine number E2059, has been installed in the top left corner at the base of the 212-foot-tall core stage. Photo credit: NASA

Technicians at NASA’s Michoud Assembly Facility in New Orleans have installed the first of four RS-25 engines on the core stage of the agency’s SLS (Space Launch System) rocket that will help power NASA’s first crewed Artemis mission to the Moon. During Artemis II, NASA astronauts Reid Wiseman, Victor Glover, Christina Koch, and CSA (Canadian Space Agency) astronaut Jeremy Hansen will launch on SLS and journey around the Moon inside the Orion spacecraft during an approximately 10-day mission in preparation for future lunar missions.

The Sept. 11 engine installation follows the joining of all five major structures that make up the SLS core stage earlier this spring. NASA, lead RS-25 engines contractor Aerojet Rocketdyne, an L3 Harris Technologies company, and Boeing, the core stage lead contractor, will continue integrating the remaining three engines into the stage and installing the propulsion and electrical systems within the structure.

All four RS-25 engines are located at the base of the core stage within the engine section, which protects the engines from the extreme temperatures during launch and has an aerodynamic boat tail fairing to channel airflow. During launch and flight, the four engines will fire nonstop for over eight minutes, consuming propellant from the core stage’s two massive propellant tanks at a rate of 1,500 gallons (5,678 liters) per second.

Each SLS engine has a different serial number. The serial number for the engine installed Sept. 11 in position two on the core stage is E2059. It along with the engine in position one, E2047, previously flew on space shuttle flights. E2047 is the most veteran engine of the entire set flying on Artemis II with 15 shuttle flights, including STS-98, which delivered the Destiny Laboratory Module to the International Space Station in 2001. The engines installed in positions three and four (E2062 and E2063) are new engines that include previously flown hardware.

NASA is working to land the first woman and first person of color on the Moon under Artemis. SLS is part of NASA’s backbone for deep space exploration, along with Orion and the Gateway in orbit around the Moon, and commercial human landing systems. SLS is the only rocket that can send Orion, astronauts, and supplies to the Moon in a single mission.

For more on NASA SLS visit:

https://www.nasa.gov/sls

Mobile Launcher Arrives at Launch Pad 39B for Artemis ll Preps

The top part of mobile launcher 1, carried by the crawler-transporter 2, rolls out from its park site location to Launch Pad 39B at NASA’s Kennedy Space Center in Florida on Aug. 16, 2023.
The mobile launcher, carried by the crawler-transporter 2, rolls out from its park site location to Launch Pad 39B at NASA’s Kennedy Space Center in Florida on Aug. 16, 2023. While at the pad, it will undergo testing for the agency’s Artemis II mission. Under Artemis, the mobile launcher will transport NASA’s Space Launch System rocket and Orion spacecraft to pad 39B for liftoff.  Photo credit: NASA/Ben Smegelsky

After an approximately four-mile journey over the course of two days, mobile launcher 1 arrived on Aug. 17 at Launch Pad 39B from its park site location at NASA’s Kennedy Space Center in Florida. It will remain at the pad for several months as teams with NASA’s Exploration Ground Systems Program prepare for Artemis ll, the first crewed mission under Artemis.

Teams will conduct a variety of tests and continue ground systems upgrades on both structures. These preparations include testing the pad’s new 1.4-million-gallon liquid hydrogen sphere and emergency egress system.

After testing at the pad is complete, the mobile launcher will travel to the Vehicle Assembly Building in preparation for rocket stacking operations ahead of launching Artemis ll.