Fueling Underway For Artemis I Launch

A view of the Interim Cryogenic Propulsion System in the Multi-Payload Processing Facility at NASA's Kennedy Space Center in Florida.
A view of the Interim Cryogenic Propulsion System inside the Multi-Payload Processing Facility at NASA’s Kennedy Space Center in Florida on Feb. 18, 2021. Photo credit: NASA/Glenn Benson

Teams with NASA’s Kennedy Space Center Exploration Ground Systems and primary contractor, Jacobs, are fueling the Orion service module ahead of the Artemis I mission. The spacecraft currently resides in Kennedy’s Multi-Payload Processing Facility alongside the Interim Cryogenic Propulsion System (ICPS), the rocket’s upper stage that will send Orion to the Moon. After servicing, these elements will be integrated with the flight components of the Space Launch System, which are being assembled in the Vehicle Assembly Building.

Technicians began loading Orion’s service module with oxidizer, which will power the Orbital Maneuvering System main engine and auxiliary thrusters on the European-built service module ahead of propellant loading. These auxiliary thrusters stabilize and control the rotation of the spacecraft after it separates from the ICPS. Once the service module is loaded, teams will fuel the crew module to support thermal control of the internal avionics and the reaction control system. These 12 thrusters steady the crew module and control its rotation after separation from the service module.

Once Orion servicing is complete, teams will fill the ICPS. This liquid oxygen/liquid hydrogen-based system will push the spacecraft beyond the Moon for the test flight under the agency’s Artemis program. In several weeks, when fueling is complete, Orion will move to the center’s Launch Abort System Facility to integrate its launch abort system, and the ICPS will move to the Vehicle Assembly Building to be stacked atop the mobile launcher.

Artemis I Orion Moves For Fueling, Next Step in Launch Preparations

Orion is buttoned up and ready to march towards the Multi-Payload Processing Facility to begin ground processing by the Exploration Ground Systems and Jacobs teams ahead of the Artemis I launch. Shielded by a protective covering for transport, the spacecraft is depart its home at the Neil Armstrong Operations and Checkout Building at NASA's Kennedy Space Center in Florida on Jan. 16, 2021.
Orion is buttoned up and ready to march towards the Multi-Payload Processing Facility to begin ground processing by the Exploration Ground Systems and Jacobs teams ahead of the Artemis I launch. Shielded by a protective covering for transport, the spacecraft departs its home at the Neil Armstrong Operations and Checkout Building at NASA’s Kennedy Space Center in Florida on Jan. 16, 2021. Photo credit: NASA/Kim Shiflett

NASA marked another milestone on the path toward the launch of Artemis I on Saturday, as engineers moved the Orion spacecraft out of the Neil Armstrong Operations & Checkout Building on its way to the Multi-Payload Processing Facility (MPPF) at the agency’s Kennedy Space Center in Florida, where the spacecraft will be fueled for its mission around the Moon.

The milestone marked completion of years of assembly and testing operations for the spacecraft and formal transfer of the spacecraft from the Orion Program and its prime contractor Lockheed Martin to NASA’s Exploration Ground Systems (EGS) team responsible for processing the vehicle, integrating it with the Space Launch System rocket, and launching them on their inaugural mission together.

The spacecraft was moved out of the O&C aboard a transport pallet and air bearing system which sits on top of a transporter. In the MPPF, it will be moved into a service stand that provides 360-degree access, allowing engineers and technicians from EGS, its lead contractor Jacobs Technology, and other support organizations to fuel and service the spacecraft. Crane operators will remove the transportation cover and use fuel lines and several fluid ground support equipment panels to load the various gases and fluids into the crew and service modules.

After Orion is fueled and engineers perform final checks in the MPPF, they will move the spacecraft to the Launch Abort System Facility, where EGS will install the Launch Abort System tower and the ogive panels that protect the crew module and LAS and provide its aerodynamic shape.

Orion is a critical component for NASA’s deep space exploration plans. During Artemis I, the spacecraft will launch on the most powerful rocket in the world and fly farther than any spacecraft built for humans has ever flown – 280,000 miles from Earth, thousands of miles beyond the Moon over the course of about a three-week mission.

Orion Loaded into Work Stand at Kennedy

Orion at Kennedy Space Center
Orion is lowered onto a work stand in the Neil Armstrong Operations & Checkout Building at NASA’s Kennedy Space Center in Florida.

Engineers loaded the Orion pressure vessel, or underlying structure of the crew module, into a work stand in the Neil Armstrong Operations & Checkout Building at NASA’s Kennedy Space Center in Florida on Feb. 2. The pressure vessel’s seven large pieces were welded together at the agency’s Michoud Assembly Facility in New Orleans between September 2015 and January 2016. It will fly thousands of miles beyond the moon on Exploration Mission-1.

The pressure vessel provides a sealed environment to support astronauts and is key for future human-rated crew modules. The Orion team will test the pressure vessel to make sure it’s structurally sound and then begin outfitting it with the spacecraft’s other systems and subsystems. Over the next 18 months, more than 100,000 components will arrive to Kennedy for integration into Orion. Check out more photos of Orion’s trip to Kennedy.