ISS Daily Summary Report – 12/22/13

Extravehicular Activity (EVA) Mobility Unit (EMU) Resize:  Following yesterday’s EVA, the feed water switch on EMU 3010 was inadvertently switched on for 2-3 seconds.  EMU suit 3010 has been declared no-go until proper drying can be performed due to concerns of water entering the sublimator. Today,  FE-3 Hopkins and FE-5 Mastracchio resized their suits such that Hopkins will wear EMU 3005 and Mastracchio will wear EMU 3011.  Additionally, both crewmembers filled their backup Liquid Cooling and Ventilation Garments (LCVGs).  Due to the amount of time required for resize and timeline review, US EVA #25 originally scheduled for Monday, December 23 has been rescheduled for Tuesday, December 24.

US EVA 25 Procedure and Dynamic Onboard Ubiquitous Graphics (DOUG) Review: Hopkins, Mastracchio, and FE-6 Wakata performed a review of Tuesday’s EVA and Space Station Remote Manipulator System (SSRMS) procedures.  The crew used the DOUG software to view the translation and robotics operation paths.  Following the reviews, the crew conducted a conference with ground specialists.

Today’s Planned Tasks

  • PILLE Prep  [Complete]
  • PHS Reminder [Complete]
  • ISERV Shutter Open [Complete]
  • BSA Battery Charge Init [Complete]
  • 52P Air Duct Removal  [Complete]
  • 52P Hatch Close and Leak Check [Complete]
  • CGBA Status Check [Complete]
  • Post EVA PHS Exam CMO [Complete]
  • Post EVA PHS Exam Subject [Complete]
  • EMU Resize [Complete]
  • LLB Charge Init [Complete]
  • REBA Install and Check out [Complete]
  • LCVG Fill  [Complete]
  • EVA Procedure Print [Complete]
  • WHC Manual Fill [Complete]
  • COЖ Maintenance [Complete]
  • EVA Procedure Review [Complete]
  • DOUG Review [Complete]
  • EVA S/G Tagup [Complete]

Task List

  • ARED Cylinder Evacuation
  • Replace KTO [Complete]
  • ЕДВ-У R&R
  • CWCI Degas
  • Roscosmos Report
  • SEINER. World Ocean Observation
  • ECON-M. Observations and Photography
  • Cosmo Shoot Troubleshoot [Complete]
  • Automated External Defibrillator (AED) Inspection
  • Oxygen Generation System (OGS) Jumper Build and Routing
  • SM PCS HD Swap
  • WinEarth HISD Photos
  • ARED Bolt Tighten
  • BCATC1
  • COL D1 FD2 MSR
  • DOS3D PDP Check
  • IFM stowage Locate
  • JAXA Report
  • Journals Nominal Entry
  • JEM WIS RSU B4 S/N 1001 Sensor  Replacement
  • Kubik 6 Belt Search
  • JPM1OF2 Lamp Housing Assembly (LHA) Replacement
  • National Engr Week Message
  • P/TV Trash
  • PPS Wipe
  • Pre-gather COL A/L
  • Pre-gather Empty CTBs
  • Recycle Tank Drain

Ground

  • Nominal Commanding

Three-Day Look Ahead:

  • Monday, 12/23:  US EVA #25 Prep, RS EVA #37 Prep
  • Tuesday, 12/24: US EVA #25
  • Wednesday, 12/25: Crew Off Duty, Holiday

QUICK ISS Status – Environmental Control Group:

                              Component Status
Elektron On
Vozdukh Manual
[СКВ] 1 – SM Air Conditioner System (“SKV1”) On
[СКВ] 2 – SM Air Conditioner System (“SKV2”) Off
Carbon Dioxide Removal Assembly (CDRA) Lab Standby
Carbon Dioxide Removal Assembly (CDRA) Node 3 Off
Major Constituent Analyzer (MCA) Lab Off
Major Constituent Analyzer (MCA) Node 3 Operate
Oxygen Generation Assembly (OGA) Standby
Urine Processing Assembly (UPA) Standby
Trace Contaminant Control System (TCCS) Lab Off
Trace Contaminant Control System (TCCS) Node 3 Full up