ISS Daily Summary Report – 03/01/15

Extravehicular Activity (EVA) 31:  Wilmore and Virts accomplished all planned objectives and one get-ahead task within a Phased Elapsed Time (PET) of 5 hours 38 minutes.  Cristoforetti and Shkaplerov assisted during suit donning and doffing activities.  The Joint Airlock egress took place at 5:52am CST and post EVA hatch closure at 11:27am CST.   Objectives accomplished during today’s EVA are as follows:

  • P3 C2V2 Boom, Antenna, and Retro-Reflector Install
  • S3 C2V2 Boom, Antenna, and Retro-Reflector Install
  • Lab MMOD Shield Removal, C2V2 Cable Route and Connect to Lab
  • Deploy and Connect P3 C2V2 Cable C and D
  • Deploy and Connect S3 C2V2 Cable A and B
  • Get-ahead task: GTEC Bag Retrieval

Today’s Planned Activities
All activities are completed unless otherwise noted.

  • PBA – Relocation for USOS EVA
  • Photo/TV EVA Camera Test
  • ISS HAM RADIO Power Off
  • US EVA – EVA CUCU Deactivation
  • Atmosphere Control and Supply (ACS) High Pressure Oxygen Bypass Configuration
  • EVA – In-Suit Light Exercise (ISLE) Preparation
  • USOS EVA Comm Config
  • CASKAD. Manual Mixing in Bioreactor
  • MORZE. Logging Liquid and Food (Medicine) Intake
  • EVA –  In-Suit Light Exercise (ISLE) Preparation
  • Atmosphere Control and Supply (ACS) High Pressure Nominal Configuration (O2)
  • EMU Prep for EVA
  • Pre-Breathe in EMU
  • VELO Exercise, Day 2
  • Crew Lock Depress
  • Post Depress and A/L Egress
  • C2V2 Installation
  • MMOD Shield Removal
  • СОЖ Maintenance. SM and FGB СВО, СГО, АСУ СПКУ Counter, POTOK Air Purification System Data Calldowns
  • MORZE. Logging Liquid and Food (Medicine) Intake
  • C2V2 Cable Routing
  • Crew Lock Ingress
  • MORZE. Prep Ops
  • Oximeter Removal
  • Configuration for EMU Glove Photography
  • Crew Lock Pre-Repress
  • Crew Lock Repress
  • Post-EVA Activities
  • CASKAD. Manual Mixing in Bioreactor
  • Return to nominal comm configuration after USOS EVA
  • MORZE. Logging Liquid and Food (Medicine) Intake
  • EVA Camera Reconfig
  • EMU Glove photos downlink
  • Start EMU Metox Regeneration
  • Reading Reminder
  • SPLANH. Experiment Timeline Review
  • Installation of Software Version 4.0 On RSE-MED Laptop
  • Inventory Audit Personal Hygiene Articles (СЛГ) and Sleep Bag Inserts (СПМ)
  • Preparation of reports for Roscosmos site
  • ECON-M. Observation and Photography
  • URAGAN. Observation and Photography
  • SM Ventilation System Preventive Maintenance. Group А 

Completed Task List Items

  • None

Ground Activities
All activities are completed unless otherwise noted.

  • System commanding associated with EVA 31

Three-Day Look Ahead:

  • Monday, 03/02:  Post EVA PHS, NMAP, Metox Regen, USOS Crew Day Off
  • Tuesday, 03/03:  40S Crew Departure Prep, FCPA R&R, Crew Handover Conference, EMU Loop Scrub
  • Wednesday, 03/04: IDA Ethernet Install, EVA Metox Regen, EMU Water Conductivity Test, Airway Monitoring Hardware Deploy, Emergency VHF Checkout, CardioOX

QUICK ISS Status – Environmental Control Group:

                              Component

Status

Elektron

On

Vozdukh

On

[СКВ] 1 – SM Air Conditioner System (“SKV1”)

On

[СКВ] 2 – SM Air Conditioner System (“SKV2”)

Off

Carbon Dioxide Removal Assembly (CDRA) Lab

Standby

Carbon Dioxide Removal Assembly (CDRA) Node 3

Operate

Major Constituent Analyzer (MCA) Lab

Idle

Major Constituent Analyzer (MCA) Node 3

Operate

Oxygen Generation Assembly (OGA)

Standby

Urine Processing Assembly (UPA)

Stop

Trace Contaminant Control System (TCCS) Lab

Off

Trace Contaminant Control System (TCCS) Node 3

Full up