ISS Daily Summary Report – 4/19/2019

Medical Proteomics: The crew performed a blood draw session in support of the JAXA Medical Proteomics experiment.  Medical Proteomics evaluates changes of proteins in blood serum, bone and skeletal muscles after space flight, and supports identification of osteopenia-related proteins. By combining research results for space mice, astronauts and ground patients, proteins related to osteopenia can be identified using the latest proteome analysis technique. It is anticipated that the use of the marker proteins related to osteopenia will be of benefit in the future for assessing the health of astronauts as well as osteoporosis patients on ground.

SUBSA (Solidification Using a Baffle in Sealed Ampoules) sample exchange: The crew removed the completed InI (Indium Iodide) sample cartridge #7 and inserted sample cartridge #5 to be processed. Both of these are solidification-from-melt samples and require up to 50hrs to be fully processed. The experiment currently running in SUBSA is the Detached Melt and Vapor Growth of InI.  InI is ideal for space experiments in the SUBSA Transparent Furnace because it’s non-toxic, has a relatively low melting point of only 365°C, and does not react or stick to the silica crucible. Directional solidification of InI from the melt can be performed at a rate of 5 mm/hr, and growth from the vapor can be performed at ~5 mm/week. This work advances the process of fabricating high-quality InI and other crystals on Earth for use as better and less expensive detectors of nuclear radiation.

Two-Phase flow 2: As a continuation of Two-Phase Flow series of experiments, the crew altered the valve settings of the Two-Phase Flow Experiment Unit. The Two-Phase Flow experiment investigates the heat transfer characteristics of flow boiling in the microgravity environment. This experiment provides a fundamental understanding of the behaviors of bubble formation, liquid-vapor flow in a tube, and how heat is transferred in cooling systems. This investigation also seeks to establish a database of thermodynamic data for microgravity boiling and two-phase flow.

Northrop Grumman 11 (NG-11):  The crew successfully captured Cygnus with the Space Station Remote Manipulation System (SSRMS) today at 4:28AM CT. Once captured, they handed off control of the SSRMS to ground Robotics Controllers who then maneuvered the vehicle to the Node 1 Nadir (N1N) Common Berthing Mechanism (CBM) interface where it was securely bolted to the ISS. Once the CBM bolting operations were complete, the crew and ground teams worked together to perform Node 1 CBM vestibule pressurization followed by hatch opening and ingress at 11:08 AM CT; NG-11 brings approximately 3426 kg of cargo to ISS.

In Flight Maintenance (IFM): As part of regularly scheduled preventative maintenance, the crew performed a manual Waste and Hygiene Compartment (WHC) flush tank fill.  By using a Post-Flight Analysis Bag to capture any pressure relief, also known as the burp, they depressurized the flush water tank and water valve block to protect the dose pump; this pump is critical as it injects the pre-treat required to properly recycle waste urine.

Public Affairs Office (PAO) Live Event: Today Nick Hague participated in a live PAO event with Military Officers Magazine and recorded a downlink message for the “Spot the Station” feature on NASA TV.

  • Military Officers Association of America (MOAA) is the nation’s largest and most influential association of military officers and today’s interview will be used in a future article highlighting Nick’s contributions in space.
  • As the third brightest object in the night sky, the International Space Station can often be seen with the naked eye when flying over the Earth at dusk or dawn. The “Spot the Station” feature will highlight today’s message and help users search for the ISS when it flies over their location.

Adlink Mini PC Remove and Replace (R&R): Today the crew replaced suspect Adlink Mini PC S/N 1001 with new unit in preparation for the Thermal Amine payload launching on SpaceX-17; the old unit failed its checkout and was stowed for later troubleshooting. 

Completed Task List Activities:

  • EVA Airlock Restow Part II.

Ground Activities:
All activities are complete unless otherwise noted.

  • SSRMS Cygnus Install and CBM Bolt Loading
  • Cygnus Hatch Open and Ingress Support

Saturday, 4/20:
Payloads:

  • Cold Stowage transfers
  • NanoRacks PF1
  • Rodent Research transfers
  • Repository
  • Tangolab-1 ops

Systems:

  • Cygnus cargo transfer
  • Cygnus OBT emergency procedure review

Sunday, 4/21:
Payloads:

  • Repository
  • Standard Measures

Systems:

  • Crew off duty

Monday, 4/22:
Payloads:

  • Fluid Shifts prep
  • LSG Crew Restraint Install/Remove
  • Rodent Research MM-1 & 2
  • Radi-N2 Neutron Field Study
  • Polar Express Rack Install & Checkout

Systems:

  • WWB bus split and WSTA fill
  • UPA Recycle Tank Fill Part 3 

Today’s Planned Activities:
All activities are complete unless otherwise noted.

  • Reminder 2F HRF Generic Frozen Blood Collection
  • Standard Measures Post-sleep Questionnaire
  • HRF Generic HRF Centrifuge Frozen Blood Collection 25 Minutes Subject
  • HRF Generic Saliva Collection 10 Minutes
  • HRF Generic HRF Centrifuge Frozen Blood Collection Operator
  • HRF Generic Sample MELFI Retrieval And Insertion Operations
  • HRF Generic HRF Centrifuge Frozen Blood Collection Configuration
  • Robotics Workstation (RWS) Configuration
  • HRF Generic HRF Centrifuge Frozen Blood Collection Spin Conclude
  • Japan Aerospace eXploration Agency Sample MELFI Insertion
  • Verifying cover closure on SM windows
  • HRF Generic Sample MELFI Insertion
  • USOS Window Shutter Close
  • Centerline Berthing Camera System (CBCS) Powerup
  • Robotic Workstation (RWS) High Definition (HD) Monitor Downlink
  • Cygnus PCS Command and PROX Link Verification
  • HRF Generic HRF Centrifuge Frozen Blood Collection Conclude And Stow
  • Inventory Management System (IMS) conference
  • Cygnus R-BAR Approach
  • ISS Crew and ГОГУ (RSA Flight Control Team) weekly conference
  • PILOT-T. Preparation for Experiment
  • Cleaning ВБП1, ВБП2 fans screens
  • Regenerative Environmental Control and Life Support System (RGN) Wastewater Storage Tank Assembly (WSTA) Fill
  • PILOT-T. Experiment Ops
  • Cygnus R-BAR Approach
  • Space Station Remote Manipulator System (SSRMS) Cygnus Capture
  • Current converter fan (ВПТ) screen cleaning
  • ISS Experience Node 1 Setup
  • Health Maintenance System (HMS) ISS Food Intake Tracker (ISS FIT)
  • Remote Workstation Monitor HD Video Downlink Deactivation RWS.
  • JEM Common Gas Support Equipment (CGSE) Lower CO2 Gas Supply Start
  • PILOT-T. Experiment Ops
  • Adlink Mini PC Swap
  • XF305 Camcorder Setup
  • Two-Phase Flow Experiment Equipment Valves Setting
  • Move 72P US temp stowed CTBs
  • In Flight Maintenance (IFM) Waste and Hygiene Compartment (WHC) Full Fill
  • ISS Experience Introduction Recording
  • ISS Experience Record Conclude
  • PCS Laptop Relocate
  • In Flight Maintenance (IFM) Waste and Hygiene Compartment (WHC) Full Fill
  • PCS Laptop Relocate
  • PILOT-T. Closeout Ops
  • Atmosphere Purification Unit (БОА) R&R in Vozdukh Atmosphere Revitalization Subsystem [СОА]. Configure Electrical Connections
  • Health Maintenance System (HMS) ISS Food Intake Tracker (ISS FIT)
  • СОЖ maintenance
  • ISS Experience Recording Preparation
  • Cygnus/Node 1 Pressurization and Leak Check Preparation
  • Monitoring [ОНА] high-gain antenna positioning for Broad-Band Communication System (ШСС) Test
  • Node 1 Centerline Berthing Camera System (CBCS) Removal
  • Solidification Using Baffles in Sealed Ampoules Sample Exchange
  • Solidification Using Baffles in Sealed Ampoules Historical Documentation Photos
  • ISS Experience Microphone Don
  • Cygnus/Node 1 Pressurization and Leak Check
  • RYASKA. Photography of plant cultivation chambers
  • Atmosphere Purification Unit (БОА) R&R in Vozdukh Atmosphere Revitalization Subsystem [СОА]. Mating Х12 Х11 telemetry connectors
  • Evacuation of Vozdukh [СОА] (start)
  • Atmosphere Purification Unit (БОА) R&R in Vozdukh Atmosphere Revitalization Subsystem [СОА]
  • Brine/urine transfer from ЕДВ to Progress 440 [AO] Rodnik H2O tank 2 and flushing H2O Tank 2 connector В2 and H2O Tank 1 connector В1
  • Evacuation of Vozdukh [СОА] (end)
  • П-16 Absorber Replacement
  • Photo TV High Definition (HD) Cygnus Video Setup
  • Public Affairs Office (PAO) High Definition (HD) Config JEM Setup
  • Atmosphere Purification Unit (БОА) R&R in Vozdukh Atmosphere Revitalization Subsystem [СОА]. Vozdukh Activation.
  • Node 1 Nadir to Cygnus Vestibule Outfitting, Part 1
  • PAO Preparation
  • Public Affairs Office (PAO) Event in High Definition (HD) – JEM
  • Atmosphere Purification Unit (БОА) R&R in Vozdukh Atmosphere Revitalization Subsystem [СОА]. Installation of LIV hardware.
  • Воздух R&R
  • Node 1 Nadir to Cygnus Vestibule Outfitting Part 2
  • БД-2 Exercise, Day 3
  • Health Maintenance System (HMS) ISS Food Intake Tracker (ISS FIT)
  • Common Berthing Mechanism (CBM) Controller Panel Assembly (CPA) Rotation and Closeout
  • Regenerative Environmental Control and Life Support System (ECLSS) Recycle Tank Drain
  • Cygnus Ingress
  • Cygnus (NG-11) Air Sampling using АК-1М sampler prior to Air Duct Installation
  • Regenerative Environmental Control and Life Support System (ECLSS) Recycle Tank Drain Part 2
  • Cygnus Cargo Photo
  • ISS Experience Microphone Doff
  • VELO Exercise, Day 3
  • БД-2 Exercise, Day 2
  • ISS Experience Hardware Relocate
  • ISS Experience Microphone Doff
  • Rodent Research Habitat Install
  • HRF Generic Urine Collection Setup
  • Restow Vestibule Outfitting Kit (VOK)
  • Rodent Research Habitat Install
  • Centerline Berthing Camera System (CBCS) Stow
  • Rodent Research Habitat Install