ISS Daily Summary Report – 1/15/16

Extravehicular Activity (EVA) #35:  Extravehicular Activity (EVA) #35:  Peake and Kopra egressed the Airlock at 7am CST in order to perform EVA #35.  During the EVA, Kopra’s carbon dioxide (CO2) sensor failed and then later he noticed a water bubble in his helmet.  Based on the trend, the Flight Control Team decided to terminate the EVA.  The Phased Elapsed Time (PET) for today’s EVA was 04:43 hours with Crew Lock ingress taking place at 11:40 pm CST.  The objectives for the EVA are as follows:

Sequential Shunt Unit (SSU) 1B:  The new SSU was successfully checked out. Ground teams are in the process of configuring the 1B channel for normal operations.

·         Remove and Replace Sequential Shunt Unit (SSU) 1B – Completed

·         Install Node 3 Non-Propulsive Vent (NPV) – Completed

·         Retrieve Camera Port 9 Light – Deferred

·         Route International Docking Adapter 3 Cables – Partially Completed

·         Mate Enhanced Processor and Integrated Communications (EPIC) MDM Ethernet Cable – Deferred

Today’s Planned Activities
All activities were completed unless otherwise noted.

  • Checking fuse LED indication on БПП-4, БПП-7 Fuse Boxes in MRM1
  • Closing USOS Window Shutters
  • ISS HAM RADIO Power Down
  • ISS Crew and ГОГУ (RSA Flight Control Team) Weekly Conference
  • Photo/TV EVA Camera Test
  • EVA CUCU Deactivation
  • EMU Preparation for US EVA
  • USOS EVA Comm Config
  • Life On The Station Photo and Video
  • OTKLIK. Hardware monitoring and sensitivity threshold adjustment
  • Vacuum Cleaning of ВД1 and ВД2 air ducts in DC1
  • EMU Prep for EVA
  • Prebreathe in EMU
  • BAR. АУ-1 Ultrasound Analyzer Repair and Recovery
  • EMU Prebreathe – Assistance
  • СОЖ Maintenance
  • Charging ТК 718 IRIDIUM Phone – Configuration setup, start charge
  • Test activation of Vozdukh Atmosphere Purification System Emergency Vacuum Valves
  • Crew Lock Depress
  • Maintenance activation of Atmosphere Purification System Emergency Vacuum Valves [АВК СОА] from the Sparest Kit (СМ1РО_3_321_1, Bag II-1/256-1, [АВК] Cover (007223R)
  • Charging ТК 718 IRIDIUM Phone – Battery Charge Status
  • Charging ТК 718 IRIDIUM Phone – Terminate Charging
  • Maintenance activation of Atmosphere Purification System  Emergency Vacuum Valves [АВК СОА] from the Spares Kit(СМ1РО_3_321_1, Bag II-1/256-1, [АВК] Cover (007223R)
  • Crew Lock Egress
  • US EVA – Preparation for SSU R&R
  • Pre-packing Russian Cargo Items for Disposal via Cygnus AO-4
  • Pumping brine and urine from EDV-U to Progress 429 (SM Aft) Rodnik H2O Tank and Flushing connector
  • ТК 719 IRIDIUM Phone Charging – Initiate Charge
  • Charging ТК 719 IRIDIUM Phone – Battery Charge Status
  • Recharging ТK 719 IRIDIUM Phone – Terminate Charge, Teardown the Setup, Closeout Ops (ФГБ1ПГО_2_224_1, CTB 1017 (002857J), Soft Container (00044322R)
  • US EVA – SSU R&R
  • Changeout of Dust Filter ПФ1-4 Cartridges in SM (ТГК431ГрО_зона1_Контейнер5.  Discard the removed items. Reflect changes in IMS)
  • US EVA – Cleanup after SSU R&R
  • MOTOCARD. Experiment Ops
  • US EVA – NPV Installation
  • US EVA – IDA 3 Cable Routing [Partially Complete]
  • MOTOCARD. Operator Assistance with the Experiment
  • Video Footage of Greetings
  • ISS Crew Handover
  • US EVA – PMA3 Bolt Release [Deferred]
  • US EVA CP9 Activities [Deferred]
  • US EVA – EPIC MDM Cable_W0087 Connection [Deferred]
  • URYSIS Setup for Operation
  • Crew Lock ingress
  • Closing USOS Window Shutters
  • EVA Glove Photo Setup
  • Return to nominal comm configuration after US EVA
  • US Post-EVA Cleanup
  • PBA relocation
  • Earth photo/video ops
  • IMS Delta File Prep

 

Completed Task List Items

  • None

 

Ground Activities

All activities were completed unless otherwise noted.

  • System commanding associated with EVA

 

Three-Day Look Ahead:

Saturday, 01/16:  USOS Airlock Deconfiguration, EVA Tool Stow, EVA debrief with ground

Sunday, 01/17: Crew Day Off

Monday, 01/18:  SPHERES, MBSU Demo Day 1

 

QUICK ISS Status – Environmental Control Group:

                              Component Status
Elektron On
Vozdukh Manual
[СКВ] 1 – SM Air Conditioner System (“SKV1”) Off
[СКВ] 2 – SM Air Conditioner System (“SKV2”) On
Carbon Dioxide Removal Assembly (CDRA) Lab Standby
Carbon Dioxide Removal Assembly (CDRA) Node 3 Operate
Major Constituent Analyzer (MCA) Lab Idle
Major Constituent Analyzer (MCA) Node 3 Operate
Oxygen Generation Assembly (OGA) Process
Urine Processing Assembly (UPA) Standby
Trace Contaminant Control System (TCCS) Lab Full Up
Trace Contaminant Control System (TCCS) Node 3 Off