ISS Daily Summary Report – 1/6/2017

Extravehicular Activity (EVA) #38: The crew opened the Airlock External Hatch at 6:22am CST and performed US EVA #38 (Lithium Ion Battery Remove & Replace (R&R) EVA #1). The Phase Elapsed Time (PET) of the EVA was 6 hours and 32 minutes. The EVA was required to install adapter plates and relocate Channel 3A Nickel Hydride (NiH2) batteries to prepare for installation of new Lithium Ion batteries. The crew completed all of the objectives for the EVA:

  • Stow Node 3 Shields on Airlock
  • Retrieve Adapter Plate A and B from the Exposed Pallet (EP)
  • Install Adapter Plate A in Slot 6
  • Relocate NiH2 Battery 4 to Adapter Plate A
  • Install Adapter Plate B in Slot 4
  • Relocate NiH2 Battery 2 to Adapter Plate B
  • Fasten H1 bolt on the Li-Ion battery in Slot 1
  • Retrieve and Install Adapter Plate C in Slot 2
  • Channel 1A Battery Prep

Additionally, the crew was able to perform two get-ahead tasks. They took photographs of the Alpha Magnetic Spectrometer (AMS), and retrieved a failed Crew and Equipment Translation Aid (CETA) Light from the S3 truss, and routed a Multiplexer/Demultiplexer (MDM) Ethernet cable along Node 1.

Today’s Planned Activities
All activities were completed unless otherwise noted.

  • Extravehicular Activity (EVA) Reminder for EVA In-Suit Light Exercise (ISLE) Preparation
  • EVA COTS UHF Communication Unit (CUCU)  Verify off
  • ISS HAM Radio and Video Power Down
  • USOS Window Shutter Close
  • Extravehicular Activity (EVA) In-Suit Light Exercise (ISLE) Preparation
  • Daily Planning Conference
  • Comm configuration for EVA
  • Download of BRI log from RSS1
  • Auditing of equipment behind FGB panel 226
  • SM Ventilation Subsystem Preventive Maintenance. Group А
  • TIMER. Experiment setup and initiation of video recording
  • PILOT-T. Preparation for the experiment
  • Extravehicular Mobility Unit (EMU) Purge
  • PILOT-T. Experiment Ops
  • Extravehicular Mobility Unit (EMU) In-Suit Light Exercise (ISLE) Prebreathe
  • Crew Medical Officer (CMO) Proficiency Training
  • PILOT-T. Experiment Ops
  • Extra-Vehicular Mobility Unit (EMU) In-Suit Light Exercise Prebreathe
  • Crewlock Depress
  • BAR Experiment Ops
  • Crewlock Post Depress
  • Crewlock Egress
  • Photodocumentation of the Crisstal experiment.
  • Photodocumentation of the EPO Pesquet Ceres
  • PILOT-T. Closeout Ops
  • S4 Battery R&R 3A Worksite Preparation
  • S4 Battery R&R Battery Adapter Plates Retrieval
  • TIMER. Experiment Ops Video Termination and Cleanup
  • Initiate water transfer from CWC-I to ЕДВ
  • SM Ventilation Subsystem Preventive Maintenance. Group А
  • Video Footage for Russia Today TV Channel
  • S4 Battery R&R Battery Adapter Plate A Installation
  • Strata Status Check
  • Terminate water transfer from CWC-I to ЕДВ
  • S4 Battery R&R Battery  4 Relocate
  • CONTENT. Experiment Ops
  • СОЖ maintenance
  • S4 Battery R&R Battery Adapter Plate B Installation
  • CONTENT. Experiment Ops
  • RS IVA Tool Kit Audit
  • S4 Battery R&R Battery  2 Relocate
  • S4 Battery R&R Battery Adapter Plate C Retrieval & Installation
  • Vacuum Cleaning of air ducts in DC1 and MRM2
  • Delta file prep
  • S4 Battery R&R Prepare 1A Battery and Cleanup 3A Worksite
  • BAR Experiment Ops
  • Crewlock Ingress
  • EVA Glove Photo Setup
  • Crewlock Repress
  • Extravehicular Activity (EVA) Crewlock Repress EVA PET end
  • Extra Vehicular Activity (EVA) Post-EVA Activities
  • Post-EVA communication reconfig
  • EVA Glove Photo Downlink
  • Photo/TV Extravehicular Activity (EVA) Camera Disassembly
  • Photo/TV Extravehicular Activity (EVA) GoPro Downlink
  • ESA PAO Recorded Message JUDO

Completed Task List Items

  • None

Ground Activities
All activities were completed unless otherwise noted.

  • Battery Set 1A3 Discharge

Three-Day Look Ahead:

  • Saturday, 01/07: Crew Off Duty, post EVA PHS, EMU H2O recharge, EVA Debrief
  • Sunday, 01/08: Crew Off Duty
  • Monday, 01/09: Crew Off Duty 

QUICK ISS Status – Environmental Control Group:

    Component

Status

Elektron

Off

Vozdukh

Manual

[СКВ] 1 – SM Air Conditioner System (“SKV1”)

Off         

[СКВ] 2 – SM Air Conditioner System (“SKV2”)

On

Carbon Dioxide Removal Assembly (CDRA) Lab

Standby

Carbon Dioxide Removal Assembly (CDRA) Node 3

Operate

Major Constituent Analyzer (MCA) Lab

Operate

Major Constituent Analyzer (MCA) Node 3

Idle

Oxygen Generation Assembly (OGA)

Standby

Urine Processing Assembly (UPA)

Standby

Trace Contaminant Control System (TCCS) Lab

Off

Trace Contaminant Control System (TCCS) Node 3

Full Up