USOS ExtraVehicular Activity (EVA) #89 RFG Retrieval Part 2: Today, astronauts Jasmin Moghbeli (EV1) and Loral O’Hara (EV2) conducted USOS EVA #89. The main goal of this EVA was to retrieve the S-Band Radio Frequency Group (RFG) and perform a Trundle Bearing Assembly (TBA) Remove and Replace (R&R) on the Port Solar Alpha Rotary Joint (SARJ). The Airlock hatch opened at 7:04 AM CDT, and the crew completed the following tasks:
Planned Tasks:
- TBA R&R and Port SARJ Lubrication [Completed]
- Remove S-Band RFG and Stanchion and Bring IVA [Deferred]
- Remove 2A H-Fixture [Completed]
- 2A BGA Imagery Survey [Deferred]
- Photograph the SASA Stanchion Jacking Bolt [Deferred]
- Remove Slack & Twist from CP8 Ethernet Cable [Completed]
Get Ahead Tasks:
- Reconfigure Starboard CETA Cart Brake Handle [Completed]
Due to insufficient time, three planned tasks were deferred. However, the crew was able to complete one get ahead task. The final Phase Elapsed Time (PET) from today’s EVA was 6 hours and 43 minutes.
Completed Task List Activities:
- None
Today’s Ground Activities:
All activities are complete unless otherwise noted.
- EVA ISLE Preparation
- EVA Prebreathe Support
- EVA HECA Camera Operations
- BGA & SARJ Commanding
- Crew Dragon Quiescent Checkout [Planned]
Look Ahead Plan
Thursday, November 2 (GMT 306)
Payloads:
- Circadian Light Data Measurement
Systems:
- SpX-29 Dragon Vehicle Operations OBT
- EVA Debrief
- EMU Water Recharge
- EVA Airlock Deconfiguration
- SSRMS LEE HD Survey
Friday, November 3 (GMT 307)
Payloads:
- Actiwatch HRF Setup
- Frost FOAM Attach
- Circadian Light Data
- CLINGERS SW Upload
- Immunity Assay Kit Gather
- ISS Ham Pass
Systems:
- SpX-29 Dragon Vehicle Operations OBT
- PEPS Inspection
- SSRMS IDA2 Survey
- SPDM Unstow
- MSS PMA2 Survey
- HMS OCT2 Exam
Saturday, November 4 (GMT 308)
Payloads:
- Thor-Davis Sessions
Systems:
- Crew Off Duty
Today’s Planned Activities:
All activities are complete unless otherwise noted.
- CMS ARED Cylinder Flywheel Evacuation
- HMS – ESA Nutritional Assessment
- EMU Purge
- EMU ISLE Prebreathe
- 2A H-Fixture Removal
- EHS TOCA WRS Sample Analysis & Data Record
- TBA Removal & Install
- SARJ Lube
- CP8 Ethernet Cable Untwist
- ESP-2 Setup & Cleanup
- Post-EVA Activities
- IFM Airlock Cleanup