Bragging Rights for Mobile Launcher Lifters and Iron Workers

A crane lifts the second of two tail service mast umbilicals up for installation on the 0-level deck of the mobile launcher on July 27, 2018, at NASA's Kennedy Space Center in Florida.
Bragg Crane and Rigging lifts the second of two tail service mast umbilicals up for installation on the 0-level deck of the mobile launcher on July 27, 2018, at NASA’s Kennedy Space Center in Florida.

Operating a heavy-lift crane and working with some of the strongest metals on Earth takes precise diligence, skill and patience. Bragg Crane & Rigging Co. of Long Beach, California, has worked in the industry since 1946, and its team members embody these skills each day as they lift and weld a launch structure that will take America back to the Moon and on to Mars.

For the past four years, Bragg Crane & Rigging Co. has been supporting Kennedy Space Center’s Exploration Ground Systems (EGS) program, playing a crucial role in preparing the program’s mobile launcher for NASA’s Artemis missions. The company has had unique opportunities to lift and install most of the critical umbilicals to the mobile launcher that will provide power to the Space Launch System (SLS) and Orion spacecraft while on the launch pad. Among the major umbilical components the company installed were the crew access arm, which will allow astronauts to climb aboard the Orion spacecraft, and the tail service mast umbilicals, which provide fuel and electrical connection to the rocket.

During peak operations, the company had approximately 120 employees assembling the launcher, bringing NASA one step closer to putting the first woman and next man on the Moon. Bragg Crane & Rigging Co. is looking forward to supporting NASA’s missions to the Moon and beyond in the coming months under a new contract to continue to prepare the Vehicle Assembly Building for the integration of the massive SLS rocket.

Rotation, Processing and Surge Facility Ready for Artemis 1

A booster lift in the Rotation, Processing and Surge Facility at NASA's Kennedy Space Center in Florida.
Technicians watch as a crane and special mechanism begin breakover, or flipping, of the mated Thrust Resistance Structure and the Guidance Control Assembly for the Orion Program’s Ascent Abort-2 flight test during practice, or pathfinder activities, June 22, 2018, inside Exploration Ground Systems’ Rotation, Processing and Surge Facility high at NASA’s Kennedy Space Center in Florida. Many pathfinding tests were completed on the flight hardware in preparation for the flight test. Photo credit: NASA/Ben Smegelsky

The Rotation, Processing and Surge Facility (RPSF) at NASA’s Kennedy Space Center in Florida will receive the solid rocket booster segments for final assembly of NASA’s Space Launch System (SLS) rocket. The agency’s Exploration Ground Systems (EGS) team successfully completed the system acceptance review and operational readiness review for the facility on July 25, 2019. This review evaluated the RPSF’s readiness to receive, process, integrate and launch flight hardware for Artemis 1 and beyond.

“The RPSF is the first processing facility at Kennedy to reach operational readiness status, and our team is looking forward to the arrival of the flight hardware so we can get to work preparing for the Artemis 1 launch,” said Mike Chappell, EGS associate program manager with lead contractor, Jacobs.

When the booster segments arrive at Kennedy, the pieces are inspected before two 200-ton cranes are positioned to lift the segments from a horizontal position to a vertical position. The RPSF also will receive the booster aft skirt from the Booster Fabrication Facility. During processing, the aft segment is attached to the aft skirt and aft exit cone.

All of the SLS solid rocket components processed in the RPSF will be transported to the Vehicle Assembly Building for final assembly with the SLS core stage and Orion spacecraft on top of the mobile launcher for the agency’s Artemis missions.

The RPSF is part of the infrastructure at Kennedy that will help NASA launch the Artemis missions and send the first woman and next man back to the Moon by 2024.

Engineers Mark Completion of Umbilical Testing at Launch Equipment Test Facility

A banner signing event was held at the Launch Equipment Test Facility.
A banner signing event was held at the Launch Equipment Test Facility at NASA’s Kennedy Space Center in Florida to mark completion of umbilical testing. Photo credit: NASA/Kim Shiflett

The team that tested the umbilical lines and launch accessories that will connect from the mobile launcher (ML) to NASA’s Space Launch System (SLS) rocket and Orion spacecraft for Exploration Mission-1 celebrated their achievement during a banner signing at the Launch Equipment Test Facility (LETF) at the agency’s Kennedy Space Center in Florida.

Engineers and technicians in the Engineering Directorate and the Exploration Ground Systems Program, along with contractor support, began the tests at the LETF about 2.5 years ago. The first to be tested was one of two aft skirt electrical umbilicals. Testing of the final umbilical, the second of two tail service mast umbilicals, was completed on June 27.

“The team of NASA test engineers and test managers, and contractor engineers and technicians, worked tirelessly six days a week, 10 hours a day, in order to meet the highly aggressive schedule and deliver the hardware to the mobile launcher for installation,” said Jeff Crisafulli, Test and Design branch chief in the Engineering Directorate.

In all, 21 umbilicals and launch accessories were tested on various simulators at the LETF that mimicked conditions during launch to ensure they are functioning properly and ready for installation on the ML. Most have been delivered and installed on the ML tower. These include the Orion service module umbilical, interim cryogenic propulsion stage umbilical, core stage forward skirt umbilical and core stage inter-tank umbilical. Two aft skirt electrical umbilicals, two aft skirt purge umbilicals, a vehicle stabilizer system, eight vehicle support posts and two tail service mast umbilicals were installed on the 0-level deck of the ML.

Before launch, the umbilical lines will provide power, communications, coolant and fuel to the rocket and spacecraft. Additional accessories will provide access and stabilization. During launch, each umbilical and accessory will release from its connection point, allowing the SLS and Orion to lift off safely from the launch pad.

“Design, fabrication and testing of the new mobile launcher’s umbilicals and launch accessories is a once-in-a-lifetime opportunity that I am proud to have been part of,” Crisafulli said.

First Tail Service Mast Umbilical Installed on Mobile Launcher for Exploration Mission-1

The first of two Tail Service Mast Umbilicals is lifted for installation on the mobile launcher July 12, 2018, at NASA's Kennedy Space Center in Florida.The first of two 35-foot-tall Tail Service Mast Umbilicals (TSMU) was lifted up and installed on the 0-level deck of the mobile launcher at NASA’s Kennedy Space Center in Florida. The installation brings the Exploration Ground Systems Program one step closer to supporting prelaunch operations for the agency’s Space Launch System (SLS) rocket and Orion spacecraft on Exploration Mission-1.

The TSMUs will connect to the SLS rocket core stage aft section and provide liquid oxygen and liquid hydrogen fluid lines and electrical cable connections to the core stage engine section to support propellant handling during prelaunch operations. This TSMU will provide the liquid oxygen.

Before launch, the TSMUs will tilt back to ensure a safe disconnect and retraction of all umbilical hardware away from the rocket during liftoff.

Photo credit: NASA/Kim Shiflett

Chilling Out During Liquid Oxygen Tank Test

The liquid oxygen tank at Launch Pad 39B at Kennedy Space Center in Florida.
A pressurization test of the liquid oxygen tank at Launch Pad 39B was completed. Photo credit: NASA/Derrick Matthews

Exploration Ground Systems (EGS) chilled out recently with a pressurization test of the liquid oxygen (LO2) tank at Launch Pad 39B at NASA’s Kennedy Space Center in Florida – Pad 39B, recently upgraded by the EGS team for the agency’s new Space Launch System rocket.

The six-hour test of the giant sphere checked for leaks in the cryogenic pipes leading from the tank to the block valves, the liquid oxygen sensing cabinet, and new vaporizers recently installed on the tank.

The SLS will use both liquid oxygen and liquid hydrogen. During tanking, some of the liquid oxygen, stored at minus 297 degrees Fahrenheit, boils off and vapor or mist is visible. While the tank can hold up to 900,000 gallons of liquid oxygen; during the test it only contained 590,000 gallons of the super-cooled propellant.

The test was monitored by engineers and technicians inside Firing Room 1 at the Launch Control Center, a heritage KSC facility also upgraded by the EGS team in preparation for the upcoming mission. Results of the test confirmed that the fill rise rate was acceptable, the tank pressurization sequence works and that only one of the two vaporizers was needed to accomplish pressurization.

Another system is “go” for the first integrated launch of SLS and the Orion spacecraft!

Last of the Big Swing Arm Umbilicals Installed on Mobile Launcher

The ICPSU is installed on the mobile launcher tower at NASA's Kennedy Space Center in Florida.
A heavy-lift crane and rigging lines are used to install the Interim Cryogenic Propulsion Stage Umbilical high up on the tower of the mobile launcher at NASA’s Kennedy Space Center in Florida. Photo credit: NASA/Ben Smegelsky

Nearly the last of several large connection lines, called umbilicals, was installed on the mobile launcher at NASA’s Kennedy Space Center in Florida. The umbilical was lifted by crane and attached high on the tower of the mobile launcher at about the 240-foot level, bringing the steel structure one step closer to supporting processing and launch of NASA’s Orion spacecraft and Space Launch System (SLS) rocket. The launcher is designed to support the assembly, testing, check out and servicing of the rocket, as well as transfer it to the pad and provide the platform from which it will launch.

This particular umbilical will supply propellants, environmental control systems, pneumatics and electrical connections to the interim cryogenic propulsion stage (ICPS) of the SLS rocket and will swing away before launch. The umbilical also will provide hazardous gas leak detection while the rocket is on the pad. The ICPS is located between the core stage of the rocket and the Orion capsule, and will provide propulsion for Orion while in space and give the spacecraft the big push needed to fly beyond the moon.

To install the umbilical, construction workers with JP Donovan prepared the rigging lines and attached the umbilical to a large crane. The ICPS umbilical was slowly lifted up and bolted to the mobile launcher. The entire process took about four hours.

With the umbilical in place, workers will install additional equipment on the tower, as well as electrical wiring, environmental control system tubing, hydraulics and other commodities will be routed to the umbilical arm before testing. Tests of the swing arm also will be performed as part of the verification and validation process.

Exploration Ground Systems is overseeing installation of the launch umbilicals and launch accessories on the mobile launcher to prepare for the first integrated test flight of Orion atop the SLS on Exploration Mission-1. A pair of tail service mast umbilicals are slated for installation later this year and will be the last of the twenty umbilicals and launch accessories to be installed on the mobile launcher. With this test flight, NASA is preparing for missions to send astronauts to deep space destinations, including the Moon, Mars and beyond.

NASA Recovery Team Completes Orion Underway Recovery Test 6 in Pacific Ocean

A test version of the Orion capsule is pulled into the well deck of the USS Anchorage during Underway Recovery Test 6.
During Underway Recovery Test 6, Kennedy Space Center’s NASA Recovery Team spent a week aboard the USS Anchorage where they and the U.S. Navy tested procedures and ground support equipment to improve recovery procedures and hardware ahead of Orion’s next flight, Exploration Mission-1, when it splashes down in the Pacific Ocean. The Orion test article sits inside the well deck of the USS Anchorage after a successful recovery test Jan. 22. Photo credit: NASA/Bill White

NASA’s Recovery Team from Kennedy Space Center just finished a week at sea, testing and improving their processes and ground support hardware to recover astronauts in the Orion capsule once they splash down in the Pacific Ocean. Aboard the USS Anchorage, NASA and the U.S. Navy worked together to run through different sea conditions, time of day and equipment scenarios—putting hardware and the people through their paces.

Astronaut Stephen Bowen was aboard as an observer to better understand the recovery procedures and to offer an astronaut’s perspective. As a former Navy captain, Bowen has a wealth of knowledge to impart to the team—helping them better understand what the crew will be going through as they are bobbing up and down in the capsule after spending time in microgravity.

“I understand what it’s like to be on a boat that doesn’t have a keel (a structural beam that runs in the middle from bow to stern to give it stability) in the open ocean,” Bowen said. “It’s not necessarily the friendliest of places to be.” And add that to the physical manifestations of re-entering a gravity environment after several weeks, Bowen’s first-hand knowledge will be paramount for the team as they hone their plans to make recovery smooth.

During the weeklong testing, the team made strides in developing the final recovery plan and even shaved 15 minutes off their best time. “When the astronauts return to Earth, we are required to retrieve them within two hours,” said NASA Recovery Director Melissa Jones, “but our goal is to get to them as quickly and safely as possible—we are shooting for half that time.”

The team still has several tests scheduled between now and Orion’s first uncrewed flight atop the new Space Launch System rocket, known as Exploration Mission-1. The mission will pave the way for future crewed missions and enable future missions to the Moon, Mars and beyond. During the flight, Orion will travel thousands of miles beyond the Moon before splashing down into the Pacific, where NASA’s Recovery Team will be ready and waiting for her.

Orion Spacecraft Recovery Rehearsal Underway

As part of Underway Recovery Test 6, the Orion test article is pulled in by a winch line at the rear of the USS Anchorage’s well deck that brings the capsule into the ship, along with four manned LLAMAs (Line Load Attenuation Mechanism Assembly) that control the capsule’s side-to-side movement and a tending line attached to a rigid hull inflatable boat for controlling Orion’s movement behind the ship. Photo credit: NASA/Bill White

NASA’s new deep space exploration systems will send crew 40,000 miles beyond the Moon, and return them safely home. After traveling through space at 25,000 miles per hour, the Orion spacecraft will slow to 300 mph after it passes through the Earth’s atmosphere. The spacecraft then slows down to 20 mph before it safely splashes down in the Pacific Ocean.

When astronauts come back from deep space, they will need to be picked up as quickly as possible. That’s where Kennedy Space Center’s NASA Recovery Team comes in.

Under the auspices of Exploration Ground Systems, Melissa Jones, NASA’s recovery director, and her team will recover the Orion capsule and crew. NASA and the U.S. Navy are working together to ensure they are ready before the first uncrewed Orion mission aboard the agency’s new Space Launch System rocket, known as Exploration Mission-1.

This week, the integrated NASA and U.S. Navy team are aboard the USS Anchorage, testing out new ground support equipment and practicing their procedures.

After Orion completes its mission out past the Moon and heads to Earth, Jones will get the call Orion is coming home. Then, it is her job to get the joint NASA and U.S. Navy team to the capsule’s location quickly and bring it and the astronauts safely aboard the U.S. Navy recovery ship.

“We are testing all of our equipment in the actual environment we will be in when recovering Orion after Exploration Mission-1,” Jones said. “Everything we are doing today is ensuring a safe and swift recovery when the time comes for missions with crew.”

Crew Access Arm for Space Launch System Arrives at Kennedy

Two heavy-lift cranes are used to tilt and lower the Orion crew access arm onto a work stand in a storage location Oct. 17, 2017, at NASA's Kennedy Space Center in Florida.
Two heavy-lift cranes are used to tilt and lower the Orion crew access arm onto a work stand in a storage location Oct. 17, 2017, at NASA’s Kennedy Space Center in Florida. The access arm was transported from Precision Fabricating and Cleaning in Cocoa, Florida. Photo credit: NASA/Kim Shiflett

When astronauts depart for missions to deep space, they will cross the Crew Access Arm about 300 feet above the ground to board their spacecraft. The access arm was delivered to NASA’s Kennedy Space Center in Florida on Oct. 17, 2017, to install on the mobile launcher in preparation for the first flight of the Space Launch System rocket, or SLS, and the Orion spacecraft.

The SLS will be the largest rocket in the world and will be stacked with Orion inside the historic Vehicle Assembly Building, or VAB, on the mobile launcher and rolled out to the pad prior to launch. The access arm will be one of 11 connection points to the rocket and spacecraft from the tower on the mobile launcher. After technicians install the arm, the mobile launcher will be rolled into the VAB for validation and verification tests.

For the first launch without crew, the access arm will provide a bridge to Orion for personnel and equipment entering the spacecraft during processing and prelaunch integrated testing while in the VAB and at the launch site. The arm is made up of two major components: the truss assembly and the environmental enclosure, or the white room. The arm will provide entry and emergency egress for astronauts and technicians into the Orion spacecraft. On future human missions, astronauts outfitted with newly designed space suits will enter the white room, where they will be assisted by technicians into the spacecraft for launch. The arm will retract before launch, and the other connections will release at liftoff, allowing the rocket and spacecraft to safely clear the launch pad.

New Umbilical Fitted for Mobile Launcher to Support NASA’s Deep Space Exploration Missions

A fit check of the core stage inter-tank umbilical is in progress on the mobile launcher tower at Kennedy Space Center in Florida
High up on the mobile launcher tower at NASA’s Kennedy Space Center in Florida, construction workers assist as a crane moves the Core Stage Inter-tank Umbilical into place for a fit check of the attachment hardware. Photo credit: NASA/Glenn Benson

Engineers lifted and installed a third umbilical on the mobile launcher at NASA’s Kennedy Space Center in Florida for a fit check. The tower on the mobile launcher will be equipped with several connections or launch umbilicals like this one. After the fit check was completed, the umbilical was lowered down and will be installed permanently at a later date.

The umbilicals will provide power, communications, coolant and fuel. They will be used to connect the mobile launcher to the agency’s Space Launch System (made up of the core stage, twin solid rocket boosters, and the interim cryogenic propulsion stage) and the Orion spacecraft mounted on top of SLS.

An area on the SLS between the liquid hydrogen and liquid oxygen tanks is known as the core stage inter-tank. The core-stage inter-tank umbilical is the third in a series of five new umbilicals for the mobile launcher. Its main function is to vent excess gaseous hydrogen from the rocket’s core stage. This umbilical also will provide conditioned air, pressurized gases, and power and data connection to the core stage.

The Orion service module umbilical and the core stage forward skirt umbilical were previously installed on the tower. The service module umbilical will connect from the mobile launch tower to the Orion service module. Prior to launch, the umbilical will transfer liquid coolant for the electronics and purge air/gaseous nitrogen for environmental control. The SLS core stage forward skirt is near the top of the core stage, and the forward skirt umbilical provides connections and conditioned air/gaseous nitrogen to the core stage of the rocket. All these umbilicals will swing away from the rocket and spacecraft just before launch.

Several other umbilicals were previously installed on the mobile launcher. These include two aft skirt purge umbilicals, which will connect to the SLS rocket at the bottom outer edge of each booster and provide electrical power and data connections, remove hazardous gases, and maintain the right temperature range with a nitrogen purge in the boosters until SLS lifts off from the launch pad.

The Ground Systems Development and Operations Program at Kennedy is preparing ground support equipment, including the launch umbilicals, for NASA’s deep space exploration missions.