NASA’s Mobile Launcher Rolls Ahead of Artemis II Preparation

Image shows NASA's mobile launcher 1 prepare to move from Launch Pad 39B to the Vehicle Assembly Building at NASA's Kennedy Space Center on Tuesday, Oct. 1, 2024.
Teams with NASA’s Exploration Ground Systems Program at the agency’s Kennedy Space Center in Florida prepare to move mobile launcher 1 atop the agency’s crawler-transporter 2 from Launch Complex 39B to the Vehicle Assembly Building on Tuesday, Oct. 1, 2024. The crawler recently reached 2,500 miles traveling to the launch pad since its construction in 1965. The mobile launcher has been at the launch pad since August 2023 undergoing upgrades and tests in preparation for NASA’s Artemis II mission. The mobile launcher will be used to assemble, process, and launch NASA’s SLS (Space Launch Systems) and Orion spacecraft to the Moon and beyond.

NASA rolled closer to integrating elements of the Artemis II Moon rocket together as teams with the agency’s Exploration Ground Systems Program at Kennedy Space Center in Florida began moving the mobile launcher 1 from Launch Complex 39B along a 4.2 mile stretch back to the Vehicle Assembly Building. First motion of the mobile launcher, atop NASA’s crawler-transporter 2, occurred at 12:09 a.m. EDT Thursday, Oct. 3.

Teams rolled the mobile launcher out to Kennedy’s Pad 39B in August 2023 for upgrades and a series of ground demonstration tests in preparation for NASA’s Artemis II mission. These preparations ranged from a launch day demonstration for the crew, closeout crew, and the pad rescue team, to testing the emergency egress system, water flow system, and the new liquid hydrogen sphere at the launch pad.

On its way to transport the mobile launcher back from the pad, NASA’s crawler-transporter 2 also achieved a milestone nearly 60 years in the making. Already designated by Guinness World Records as the heaviest self-powered vehicle – larger than a baseball infield and weighing approximately 6.65 million pounds – the crawler reached 2,500 miles traveled since its construction in 1965.

The mobile launcher is expected to arrive outside the Vehicle Assembly Building around 10 a.m. Thursday, Oct.3, before the Exploration Ground Systems teams move it into High Bay 3 on Friday, Oct.4.

Follow the livestream of the mobile launcher on the move.

 

 

 

 

NASA’s Rocket On Roll: Core Stage Arrives at Vehicle Assembly Building

After completing its journey from NASA’s Michoud Assembly Facility in New Orleans aboard the Pegasus barge, teams with Exploration Ground Systems (EGS) transport the agency’s powerful SLS (Space Launch System) core stage to NASA’s Kennedy Space Center’s Vehicle Assembly Building in Florida on Tuesday, July 23, 2024. Once inside, SLS will be prepared for integration atop the mobile launcher ahead of the Artemis II launch.
After completing its journey from NASA’s Michoud Assembly Facility in New Orleans aboard the Pegasus barge, teams with Exploration Ground Systems (EGS) transport the agency’s powerful SLS (Space Launch System) core stage to NASA’s Kennedy Space Center’s Vehicle Assembly Building in Florida on Tuesday, July 23, 2024. Photo credit: NASA/Isaac Watson

NASA’s SLS (Space Launch System) rocket core stage for the Artemis II mission is inside the Vehicle Assembly Building at the agency’s Kennedy Space Center in Florida.

Tugboats and towing vessels moved the barge and core stage 900-miles to the Florida spaceport from NASA’s Michoud Assembly Facility in New Orleans, where it was manufactured and assembled.

Team members with NASA’s Exploration Ground Systems Program safely transferred the 212-foot-tall core stage from the agency’s Pegasus barge, which arrived at NASA Kennedy’s Complex 39 turn basin wharf on July 23, onto the self-propelled module transporter, which is used to move large elements of hardware. It was then rolled to the Vehicle Assembly Building transfer aisle where teams will process it until it is ready for rocket stacking operations.

In the coming months, teams will integrate the rocket core stage atop the mobile launcher with the additional Artemis II flight hardware, including the twin solid rocket boosters, launch vehicle stage adapter, and the Orion spacecraft.

The Artemis II test flight will be NASA’s first mission with crew under the Artemis campaign, sending NASA astronauts Victor Glover, Christina Koch, and Reid Wiseman, as well as CSA (Canadian Space Agency) astronaut Jeremy Hansen, on a 10-day journey around the Moon and back.

NASA’s Artemis II Orion Spacecraft Prepares for Vacuum Testing

The Artemis II Orion spacecraft is pictured surrounded by the metal walls of the altitude chamber
Technicians used a 30-ton crane to lift NASA’s Orion spacecraft on Friday, June 28, 2024, from the Final Assembly and System Testing (FAST) cell to the altitude chamber inside the Neil A. Armstrong Operations and Checkout building at NASA’s Kennedy Space Center in Florida. The spacecraft, which will be used for the Artemis II mission to orbit the Moon, underwent leak checks and end-to-end performance verification of the vehicle’s subsystems.

NASA’s Orion spacecraft for the Artemis II mission was lifted out of the Final Assembly and System Testing cell on June 28 inside the Neil A. Armstrong Operations and Checkout building at NASA’s Kennedy Space Center in Florida. The integrated spacecraft has been undergoing final rounds of testing and assembly, including end-to-end performance verification of its subsystems and checking for leaks in its propulsion systems.

A 30-ton crane returned Orion into the recently renovated altitude chamber where it underwent electromagnetic testing. The spacecraft now will undergo a series of vacuum chamber qualification testing. The tests will subject the spacecraft to a near-vacuum environment by removing air, thus creating a space where the pressure is extremely low. This results in no atmosphere, similar to the one the spacecraft will experience during future lunar missions.

Testing will span approximately a week, with technicians collecting data from the spacecraft’s chamber, cabin, and the environmental control and life support system to test spacesuit functionality. The data recorded during these tests will be used to qualify the spacecraft to safely fly the Artemis II astronauts through the harsh environment of space.

Artemis II Orion Crew Module Acoustic Testing Complete

Artemis II crew members, shown inside the Neil Armstrong Operations and Checkout Building at NASA’s Kennedy Space Center in Florida, check out their Orion crew module on Aug. 8, 2023. From left are: Victor Glover, pilot; Reid Wiseman, commander; Christina Hammock Koch, mission specialist; and Jeremy Hansen, mission specialist. The crew module is undergoing acoustic testing ahead of integration with the European Service Module. Artemis II is the first crewed mission on NASA’s path to establishing a long-term lunar presence for science and exploration under Artemis.
Artemis II crew members, shown inside the Neil Armstrong Operations and Checkout Building at NASA’s Kennedy Space Center in Florida, check out their Orion crew module on Aug. 8, 2023. From left are: Victor Glover, pilot; Reid Wiseman, commander; Christina Hammock Koch, mission specialist; and Jeremy Hansen, mission specialist. The crew module is undergoing acoustic testing ahead of integration with the European Service Module. Artemis II is the first crewed mission on NASA’s path to establishing a long-term lunar presence for science and exploration under Artemis. Photo credit: NASA/Kim Shiflett

On Aug. 13, engineers and technicians inside the high bay of the Neil Armstrong Operations and Checkout Building at NASA’s Kennedy Space Center in Florida successfully completed a series of acoustic tests to ensure the Orion spacecraft for NASA’s Artemis II mission can withstand the speed and vibration it will experience during launch and throughout the 10-day mission around the Moon, the first Artemis mission with astronauts.

During the testing, engineers surrounded the crew module with large stacks of speakers, and attached microphones, accelerometers, and other equipment to measure the effects of different acoustic levels. Engineers and technicians will now analyze the data collected during the tests.

Prior to testing, the four Artemis II astronauts visited the high bay and viewed their ride to the Moon. With this test complete, technicians at Kennedy are on track to integrate Orion’s crew and service modules this fall.

Artemis II Crew Visits Naval Base San Diego for Recovery Training

Artemis II astronauts inside the Vehicle Advanced Demonstrator for Emergency Recovery (VADR) during a tour of Naval Base San Diego.
From left (front to back), NASA astronauts Victor Glover, Christina Hammock Koch, and Reid Wiseman, along with Canadian Space Agency astronaut Jeremy Hansen, pose inside the Vehicle Advanced Demonstrator for Emergency Recovery (VADR) during a tour of Naval Base San Diego on July 19, 2023. VADR is a replica of the Orion crew module that will carry the astronauts around the Moon on Artemis II. Photo credit: U.S. Navy/Mass Communication Specialist 2nd Class Joshua Samoluk

The Artemis II crew – NASA astronauts Reid Wiseman, Victor Glover, Christina Hammock Koch, and Canadian Space Agency astronaut Jeremy Hansen – visited Naval Base San Diego on July 19 ahead of the first Artemis II recovery test in the Pacific Ocean, Underway Recovery Test-10. The test will build on the success of Artemis I recovery and ensure NASA and the Department of Defense personnel can safely recover astronauts and their Orion spacecraft after their trip around the Moon on the first crewed Artemis mission.

The crew met with recovery team members from NASA’s Exploration Ground Systems Program and the Department of Defense to learn more about the recovery process for their mission, which includes being extracted from the spacecraft after splashing down in the Pacific Ocean and being lifted via helicopter to the recovery ship where they will undergo routine medical checks before returning to shore.

The visit included a walkdown of the ground equipment and facilities the team uses to practice recovery procedures along with a walkthrough of the recovery ship. The crew will participate in full recovery testing at sea next year.

Orion Heat Shield Installed for NASA’s Artemis II Mission

The heat shield for the Artemis II Orion spacecraft
Installation of the heat shield for the Artemis II Orion spacecraft was recently completed at NASA’s Kennedy Space Center in Florida. Photo credit: NASA/Cory Huston

On June 25, 2023, teams completed installation of the heat shield for the Artemis II Orion spacecraft inside the high bay of the Neil Armstrong Operations and Checkout Building at NASA’s Kennedy Space Center in Florida.

The 16.5-foot-wide heat shield is one of the most important systems on the Orion spacecraft ensuring a safe return of the astronauts on board. As the spacecraft returns to Earth following its mission around the Moon, it will be traveling at speeds of about 25,000 mph and experience outside temperatures of nearly 5,000 degrees Fahrenheit. Inside the spacecraft, however, astronauts will experience a much more comfortable temperature in the mid-70s thanks to Orion’s thermal protection system.

Up next, the spacecraft will be outfitted with some of its external panels ahead of acoustic testing later this summer. These tests will validate the crew module can withstand the vibrations it will experience throughout the Artemis II mission, during launch, flight, and landing.

Once acoustic testing is complete, technicians will attach the crew module to Orion’s service module, marking a major milestone for the Artemis II mission, the first mission with astronauts under Artemis that will test and check out all of Orion’s systems needed for future crewed missions.

Orion ‘Powerhouse’ for Artemis II Arrives at Kennedy

The European Service Module (ESM) for NASA’s Orion spacecraft arrives at the Launch and Landing Facility at NASA’s Kennedy Space Center in Florida on Thursday, Oct. 14, 2021.
The European Service Module for NASA’s Orion spacecraft arrives at the Launch and Landing Facility at NASA’s Kennedy Space Center in Florida on Thursday, Oct. 14, 2021. Making the journey from the Airbus Facility in Bremen, Germany, aboard a Russian Antonov aircraft, the service module will be transferred to Kennedy’s Neil A. Armstrong Operations and Checkout Facility. Photo credit: NASA/Isaac Watson

Built by teams at ESA (European Space Agency) and aerospace corporation Airbus, the European Service Module for NASA’s Orion spacecraft arrived at NASA’s Kennedy Space Center in Florida on Thursday, Oct. 14, aboard the Russian Antonov aircraft. This service module will be used for Artemis II, the first Artemis mission flying crew aboard Orion. Service module assembly was completed at the Airbus facility in Bremen, Germany, and the module traveled across the world on its journey to Kennedy.

The service module is the powerhouse that will fuel and propel Orion in space. It stores the spacecraft’s propulsion, thermal control, electrical power, and critical life support systems such as water, oxygen, and nitrogen.

The service module will be transferred from the Launch and Landing Facility to Kennedy’s Neil A. Armstrong Operations and Checkout Facility where teams from NASA and Lockheed Martin will integrate it with the crew module adapter and crew module, already housed in the facility.

With Artemis missions, NASA will land the first woman and the first person of color on the lunar surface. Artemis II will be the first crewed flight test of NASA’s Space Launch System and Orion, paving the way for human exploration to the Moon and Mars.

Under Pressure! New Rainbird System Will Protect Artemis II

Water spraying out of a nozzle for rainbird testing for the Artemis II mission.
Water flows through a small-scale, 3D-printed nozzle during prototype testing of a new rainbird system on March 24, 2021, at NASA’s Kennedy Space Center in Florida. Photo credit: NASA/Ben Smegelsky

As NASA prepares for the uncrewed Artemis I test flight, teams at the agency’s Kennedy Space Center are also hard at work getting ready for the Artemis II mission that will send astronauts on a trip around the Moon ahead of a crewed lunar landing.

Water flows through large nozzles during rainbird testing for the Artemis II mission.
Teams with NASA’s Exploration Ground Systems and supporting contractors conduct prototype testing of a new rainbird system at the agency’s Kennedy Space Center in Florida on March 24, 2021, that can be used for the crewed Artemis II mission to the Moon. Photo credit: NASA/Ben Smegelsky

This includes assessing a new prototype “rainbird” system designed to protect the mobile launcher – as well as NASA’s Space Launch System (SLS) – when the engines roar to life. The March 24 tests included running various water pressures through small-scale, 3D-printed nozzles to capture data that can be used to develop full-scale hardware.

The rainbirds will release enough water to fill 40 swimming pools in 40 seconds. This massive volume will help absorb the heat and energy when SLS, the most powerful rocket the agency has ever built, lifts off with the Orion spacecraft from Kennedy’s Launch Pad 39B.

While upgraded rainbirds – large-scale water nozzles – have already been tested and installed on the mobile launcher for the Artemis I launch, Exploration Ground Systems (EGS) found room for improvement. This led teams from EGS and supporting contractors to start testing another prototype system to distribute water more evenly to maximize performance ahead of the Artemis II launch.

Water flows through a nozzle during rainbird testing for the Artemis II mission.
Alongside the iconic Vehicle Assembly Building at NASA’s Kennedy Space Center in Florida, teams with the agency’s Exploration Ground Systems and supporting contractors conduct prototype testing of a new rainbird system on March 24, 2021. Photo credit: NASA/Ben Smegelsky

“By running our prototype through a range of pressures, we can simulate what each of the rainbirds will see on the mobile launcher on launch day and have a better understanding of how they will perform when we scale them back up to full size,” said Dave Valletta, a design engineer at Kennedy working on the ignition overpressure protection and sound suppression (IOPSS) system.

A critical piece of the IOPSS system, the rainbird got its name decades ago when space shuttle developers noted that it looked like a garden sprayer.

“When we saw the pattern of the water discharge during the first test flow in the shuttle program, it reminded us of your common lawn sprinkler, only it did not rotate and was 100 times the size,” said Jerry Smith, a design engineer for mechanical-fluid systems at Kennedy.

Once prototype testing is complete, allowing better prediction of future spray patterns, the team will move forward with designing a preferred concept. That concept will be built and installed on the mobile launcher to undergo verification and validation testing, where the newly installed nozzles will be fully integrated with the launch pad to ensure they work as expected.

“The confidence check gained from these tests will lead us to developing full-scale nozzles for the mobile launcher,” said Gerald Patterson, IOPSS and fire suppression system operations engineer and test lead. “Once installed, they’ll provide more efficient water distribution across the deck and, ultimately, better protection to ground systems, the SLS rocket, and its crew for Artemis II and beyond.”

Launch Abort Motor for Orion’s Artemis II Mission Arrives at Kennedy Space Center

The launch abort system motor for the Artemis II mission arrives at Kennedy Space Center on April 13, 1970.
The launch abort motor for Orion’s launch abort system (LAS) for Artemis II, enclosed in its shipping container, arrives at NASA’s Kennedy Space Center in Florida on April 13, 2020. The motor arrived from Northrop Grumman in Promontory, Utah, and was transported to the Launch Abort System Facility where it will undergo testing in preparation for the second Artemis mission. The launch abort motor is one of three motors on the LAS. The LAS will be positioned atop the Orion crew module and is designed to protect astronauts if a problem arises during launch by pulling the spacecraft away from a failing rocket. Artemis II will take the first humans in orbit around the Moon in the 21st century.

Kennedy Space Center has received a critical piece of hardware in support of the Artemis II crewed mission. The launch abort motor for Orion’s Launch Abort System (LAS) arrived in Florida April 13 from Northrop Grumman in Promontory, Utah, and was transported to the Launch Abort System Facility where it will undergo testing in preparation for use on the second Artemis mission.

The launch abort motor is one of three motors on the LAS and is capable of producing about 400,000 pounds of thrust to steer and pull the crew module away from the rocket. The attitude control motor and the jettison motor complete the trio of motors responsible for controlling the LAS.

The LAS weighs about 16,000 pounds and is installed on top of the Orion crew module. It is designed to protect astronauts in the unlikely event of an emergency during launch or ascent. The system pulls the spacecraft away from a falling rocket and reorients the crew module to provide a safe landing for the crew.

Under the Artemis program, NASA will land the first woman and next man on the Moon. Orion will launch atop the agency’s Space Launch System rocket to carry astronauts to space, provide emergency abort capability, sustain the crew during space travel, and provide safe re-entry from deep space return velocities. NASA will develop a sustainable presence at the Moon and apply knowledge gained to pave the way for human exploration of Mars.